WORKS ON CONSTRUCTION OF THE RAILWAY SECTION STARA PAZOVA - NOVI SAD, WITHIN THE FRAMEWORK OF RECONSTRUCTION, MODERNIZATION AND CONSTRUCTION OF THE DOUBLE TRACK RAILWAY LINE BELGRADE - STARA PAZOVA - NOVI SAD - SUBOTICA – STATE BORDER WITH HUNGARY (36,2 k

Investor: 
Serbian Railways Infrastructure JSC


Project value: 
USD 255,627,932.73


Source of financing: 
Russian Loan (85% of the total project value) and participation of the Republic of Serbia (15% of the total project value)


Designer: 
Institute of Transportation CIP

 

Contractor: 
RZD International


Supervision: 
Project Biro Utiber d.o.o. (leading member of the bidding group)


Project significance: 
The reconstruction and modernization project of the railway section Stara Pazova - Novi Sad is of strategic importance considering that it is part of the core transversal network of the Republic of Serbia and as such is part of the route of the future high-speed railway line between Belgrade and Budapest.

 

Project status: 
Works are in progress.

 

• Percentage of physical realization on 21 May 2021: 82,56%
• Percentage of financial realization on 21 May 2021: 85,17%.

 

So far, all 40.5 km of the Stara Pazova – Novi Sad high-speed railway line have been completed. Of that total length of the railway line, 34.1 km is an open railway line (left and right track together) on the Stara Pazova – Beška section, as well as 5.4 km of station tracks at the Indjija station.

 

Project start date: 
16 March 2018

 

Project completion date: 
31 December 2021