Construction of the E-761 highway, Belgrade-Sarajevo, section: Sremska Raca - Kuzmin

Project carrier: 

Ministry of Construction, Transport and Infrastructure

Project title: 

Construction of the E-761 highway, Belgrade-Sarajevo, section: Sremska Raca - Kuzmin

Investor: 

Ministry of Construction, Transport and Infrastructure, PE Roads of Serbia

Contractor: 

TASYAPI INSAAT TAAHHUT SANAYI VE TICARET A.S. Belgrade Branch

Supervision: 

temporary supervision of PE Roads of Serbia

Designer: 

CIP Traffic Institute, TASYAPI INSAAT TAAHHUT SANAYI VE TICARET A.S. branch Belgrade

The significance of the project: 

In addition to linking the capitals of the Republic of Serbia and Bosnia and Herzegovina, there is also a link with Pan-European Corridors: Corridor 4, Corridor 5, Corridor 7 (Danube River) and Corridor 10. In addition, the construction of Pozega – Uzice – Border crossing with Bosnia and Herzegovina (Kotroman) is also creating a connection with Milos the Great highway and the future E-761 highway, Morava Corridor, in the Republic of Serbia.

 

Status of the project: 

In December 2019, detailed regulation plans were adopted for the entire highway in RS. The Urban Plan was also adopted as a planning document for the construction of Sava Bridge. Location conditions for Sava Bridge were obtained and the Feasibility Study with the preliminary design was adopted by the Audit Committee on June 24th 2019. Preparation of the Project for the construction permit for Phase 1 of Sava Bridge has been completed and a positive Technical Control Report has been obtained.

Construction of construction camps, installation of mechanization (mechanical base, asphalt base, etc.) and laboratories are underway. Preparatory work and pile-laying are being carried out.

Investment value: 

250.000.000 euros

Start of the project: 
  1. 31.8. 2019.
Completion of the project: 

December 2023

Source of finance: 

loan from Turkish banks and the budget of the Republic of Serbia

Project description: 

Sremska Raca - Kuzmin section, with a total length of about 18 km with a bridge over Sava River, is part of the project for construction of E-761 highway, Belgrade-Sarajevo. In addition, the construction of Pozega-Kotroman section (approximately 60 km long) is also planned in the Republic of Serbia. Commercial agreement with Tasyapi company foresees that EUR 25 million be earmarked for the preparation of planning and technical documentation for this section.

The section of Sremska Raca - Kuzmin highway will be designed for a maximum speed of 130 km / h and will have two lanes and one stop lane in both directions. It is envisaged that the future road will pass through Kuzmin all the way to the existing border crossing at Sremska Raca, where the bridge over Sava River will be built in the length of about 1.3 km.