Construction of a Class IB Expressway, Bački Breg Border Crossing – Sombor – Kula – Vrbas – Srbobran – Bečej – Kikinda – Border Crossing Srpska Crnja
Ministry of Construction, Transport and Infrastructure of the Republic of Serbia
Construction of a Class IB Expressway, Bački Breg Border Crossing – Sombor – Kula – Vrbas – Srbobran – Bečej – Kikinda – Border Crossing Srpska Crnja
Government of the Republic of Serbia, Ministry of Construction, Transport and Infrastructure (financier)
Azvirt - branch Belgrade
„Corridors of Serbia“ LLC
MHM-PROJECT ltd Novi Sad
- General Transport Master Plan in the Republic of Serbia 2009-2027;
- Agreement on Economic and Technical Cooperation in the Field of infrastructure between the Government of the Republic of Serbia and the Government of the Republic of Azerbaijan, signed on01.2012 in Baku;
- Conclusion of the Government of the Republic of Serbia from 08.2021 which recognizes the construction of a class IB expressway, border crossing Bački Breg – Sombor – Kula – Vrbas – Srbobran – Bečej – Kikinda – border crossing Srpska Crnja as a project of special significance for the Republic of Serbia;
- Framework Commercial Agreement on the Design and Construction of the Expressway, border crossing Bački Breg – Sombor – Kula – Vrbas – Srbobran, between the Government of the Republic of Serbia and the Azerbaijan company „AzVirt“, branch in Belgrad from 03.2026;
- Relevant Annex 1 of the Framework Commercial Agreement on the Design and Construction of the Expressway, border crossing Bački Breg – Sombor – Kula – Vrbas – Srbobran, between the Government of the Republic of Serbia and the Azerbaijan company „AzVirt“, branch in Belgrad from03.2026;
- Direct Contracting pursuant to the Intergovernmental Agreement between the Government of the Republic of Serbia and the Government of the Republic of Azerbaijan;
This road represents a highly significant road communication route, which connects Serbia with Hungary and Romania. The location of the section demonstrates its importance and role in the region from an economic perspective. The alignment of the future expressway in question will provide a connection between Bačka and Banat and central and western Serbia via the Belgrade – Subotica motorway.
The Chinese company, the previos contractor, has finished a part of previous works on Section 1 for Phase 1, that were not included in the bid of the new contractor “AzVirt“.On 18.03.2026 the Framework Commercial Agreement on Design and Construction of the expressway, border crossing Bački Breg – Sombor – Kula – Vrbas – Srbobran, was signed between the Government of the Republic of Serbia and the Azerbaijan company “AzVirt”, branch Belgrade. On 18.03.2026 the Relevant Annex 1 of the Framework Commercial Agreement on Design and Construction of the expressway, border crossing Bački Breg – Sombor – Kula – Vrbas – Srbobran was signed between the Government of the Republic of Serbia and the Azerbaijan company “AzVirt”, branch Belgrade. The contractor commences the works for Phase 1 (date of commencement) once all preconditions for the commencement date have been met.
The contracted value is 240,384,288.96 EUR for the construction of Section 1 and design of Sections 1, 2, 3, 4 and 5.
The Contractor pre-finances the execution of the works from the loan funds in the form of an advance payment. Once the necessary conditions have been met, the project will be financed from the funds provided under the Loan Agreement, from the budget of the Republic of Serbia, or from other sources of financing.
The alignment of the expressway has been designed from the border crossing with Hungary (Bački Breg) via Sombor – Kula – Vrbas – Srbobran – Bečej – Novi Bečej – Kikinda to the border crossing with Romania (Srpska Crnja), and is divided into the following sections:
- Section 1: Bački breg – interchange „Sombor”, 22.7 km in length;
- Section 2: Interchange „Sombor“ – Kula municipality boundary, 18.1 km in length;
- Section 3: Kula municipality boundary – Vrbas municipality boundary, 26.4 km in length;
- Section 4: Vrbas municipality boundary – Srbobran municipality boundary/A1/E75 – Vrbas Interchange, 14.3 km in length;
- Section 5: Srbobran municipality boundary/А1/Е75-interchange Vrbas – Bečej municipality boundary, 12.7 km in length;
- Section 6: Bečej municipality boundary – Novi Bečej municipality boundary, river Tisa, 18.8 km in length;
- Section 7: Novi Bečej municipality boundary river Tisa – Kikinda City boundary (Danube – Tisa – Danube Canal, Kikinda Canal), 35.1 km in length;
- Section 8: Kikinda City boundary (Danube – Tisa – Danube Canal, Kikinda Canal) –
interchange „Kikinda East” and from the interchange „Kikinda Istok” in direction of Nakovo, 17. 7 km in length and
- Section 9: from the interchange „Kikinda East” to the border crossing with Romania (Srpska Crnja), 19.7 km in length.
The construction of 46 bridges (over canals and road crossings), 34 overpasses, 5 underpasses, and 35 culverts is planned, along with 12 grade-separated intersections (interchanges), namely: Sombor, Kljajićevo, Sivac, Crvenka, Kula, Vrbas West, Vrbas North, Vrbas East, Vrbas E-75, Srbobran North, Turija, and Kikinda East. In addition, the construction of 13 at-grade roundabouts is planned.